Page 1

3 Single Site Verification
About This Chapter

The single site verification is a process of checking whether the functions of the equipment on
sites and in cells are normal. The purpose is to ensure the basic functions, such as access,
communication, and handoff, of the cells in the sites before starting RF optimization.

Single site verification helps to isolate problems due to equipment malfunction from the
problems to be solved during network optimization. For example, single site verification helps
to isolate call drop problems and access problems due to equipment malfunction from call drop
problems and access problems due to poor network coverage. Problem isolation helps to identify
and solve the problems and improve the network optimization efficiency.

Also, the single site verification can help the optimization engineers to know the site positions,
site configuration, and the surrounding radio environments in the areas to be optimized. The
single site verification is the basis for the future optimization.

3.1 Input and Output of Single Site Verification
Before starting single site verification, make related engineering parameter tables ready. After
single site verification, write corresponding engineering reports and make corresponding
records.

3.2 Tools for Single Site Verification
This describes software and hardware tools required in the single site verification.

3.3 Process of Single Site Verification
This describes the process of single site verification. Single site verification involves
preparations, single site test, and troubleshooting.

3.4 Preparations for the Single Site Test
Before starting a single site test, make a list of the cells under test ready, check site status, collect
and check data configuration, and select test location.

3.5 Test of a Single Site
Single site test involves verifying the site configurations, signal coverage of the site, and services
in the site.

cBSS
Network Optimization Guideline 3 Single Site Verification

Issue 2.0 (2008-03-10) Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd

3-1

Page 4

Table 3-3 Description of the single site verification process

Process Task

Preparations
for the
single site
test

Before starting single site verification, make the Engineering Parameter
table and the Cell Parameter table written out during network planning ready.
After checking the data configuration, write out the Radio Parameter
Configuration Data table.
During the test preparation, check the site status and configuration data and
select the test points.

Test of a
single site

According to the Single Site Verification Checking table, check whether any
problem about the engineering installation or equipment functionality exists
in any site. Write out a Single Site Verification Checking table for each site.

Troublesho
oting

Identify and solve equipment functionality problems by project engineers and
product support engineers.



3.4 Preparations for the Single Site Test
Before starting a single site test, make a list of the cells under test ready, check site status, collect
and check data configuration, and select test location.

Table 3-4 describes how to prepare for a test.

Table 3-4 Preparations for a single site test

Task Description

Checking site
status

Before the site test, prepare the list of the cells in the areas (a site or more
sites) under test, and ensure that the status of the cells under test is normal.

Collecting and
checking the data
configuration

Before starting the site test, collect the data configuration documents
created in the network planning and collect the data configuration stored
on the BAM database. Then, check and ensure that the actual data
configuration is consistent with the planned data configuration.

Selecting the test
location

To ensure that the tested services are provided in the test cell, ensure that
the signal strength in the test cell is stronger than the signal strengths in
its neighbor cells.

Other
preparations

l Check whether the transmission power of every site is allowed.

l Obtain the IMSI of the test terminal.

l Ensure that the test MS is in project mode or that the AT uses the data
card in project mode, and the MS or AT has adequate power.

l Print the test tables in papers.

l Before starting the site test, collect the information about the test BTS,
including the site location, cell ID, PN code, omnidirectional site or
directional site configuration, and antenna azimuth.



3 Single Site Verification
cBSS

Network Optimization Guideline

3-4 Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd

Issue 2.0 (2008-03-10)