METHOD STATEMENT FOR CONSTRUCTION OF BOX CULVERTS 

 

SCOPE OF WORK 

As cross‐main drainage structures, box culverts will be constructed at instructed locations by the 

Supervisor’s Representative to replace hydraulically inadequate pipe culverts. 

METHOD 

A site store has been set‐up to stock materials including cement and reinforcing steel. Mobilization of 

plant and equipment will commence upon receipt of a go ahead/ site instruction to commence work on 

the culverts.  

The main works will include activities such as setting out, excavations, blinding, reinforcement and 

formwork, batching, mixing and casting, curing and backfilling. 

All works will only commence upon acceptance and/or approval of previously completed work at every 

stage of the construction. 

Safety precautions are to be adhered by ensuring that, all plants are operated by authorized operators. 

Besides, all workers in the concrete section will be provided with safety gears including dust masks, 

hand gloves, gumboots, helmets, goggles and others as applicable. 

 

DESCRIPTION OF OPERATIONS 

Activity  Details/ Description  Plant  labor 

Setting out  
 
 
 
 
 
Excavations 

A survey team consisting of one surveyor, 
two assistances and four chainmen will 
take levels and set out the excavation 
area by use of pegs to mark points on the 
ground.  
 
Upon acceptance of the setting out by 
the S.R, excavations will be done by use 
of a back hoe loader to the satisfaction of 
the S.R. 
 
Excavated levels will be taken after 
acceptance of excavations. 

2 No. Pick up 
 
1 No. back hoe 
loader 
 
 

1 No. surveyor 
 
2 No. assistance 
 
4 No. chainmen 
 
2 N o. driver 
 
1 No. operator 
 
1 No. foreman